Screen Shot 2023-02-15 at 12.23.38 AM.png

WHISTLE PIG TANK IMPROVEMENTS


STRUCTURAL CONCRETE, EXCAVATION AND BACKFILL, SITE PIPING, PROCESS PIPING AND EQUIPMENT

JC Constructors recently completed this water tank project consisting of a buried 2.75MG AWWA Type 1 pre-stressed tank with associated piping, pressure reducing valves and a control building. 

The site was selected by Veolia on the Birds of Prey ground due to its ideal site elevation in proximity to Veolia’s high pressure transmission line.  Permission was granted on the condition it would not be very noticeable.

The tank is a large, 120’ diameter, 35’ sidewall tank, 32 interior columns, and a heavily reinforced concrete deck. JCC crews excavated nearly 20,000 CY into the steep hillside site to place the base slab.  Work progressed with 35’ high wall forms and taller column forms, all work by JCC crews.  Following subcontracted pre-stressing, JCC installed a very extensive 370,000 CF shoring system to support, form and place the heavy deck.  The tank was then backfilled with up to 60’ plus fills with an extensive slope stability effort.  Included in the fill effort was room for a new 800’ site access road across the very steep terrain.  The project is now buried, the site is re-graded and re-seeded, and few will know it exists.

WHERE OUR EXPERTISE CAME IN